MVA Bonn
More than 1,000 tonnes of waste are delivered to the waste recycling plant (MVA) in Bonn on working days. SWB Verwertung uses state-of-the-art technology to recover energy from the waste.
The waste incineration plant in Bonn produces steam when incinerating waste, which is delivered to the neighbouring SWB combined heat and power plant. Here, steam is turned into electricity and district heating.
Facts and figures
- Year of construction 1992
- Commissioning of the new delivery bunker in 2015
- Incineration lines 3
- Ø annual capacity 250,000 tonnes
- Returo ensures full capacity utilisation
Energy generation
- Steam supply approx. 500,000 MWh
Conversion to electricity and district heating in the SWB cogeneration plant
- Electricity generation approx. 97,000 MWh
Production of district heating approx. 182,000 MWh
Approach/ Opening hours
Location address | Contact details | Opening hours |
Am Dickobskreuz | Phone: +49 (0)228 7117200 | Monday to Friday: |
(Approach gate 1) | E-mail: mva-kundenservice@stadtwerke-bonn.de | 06:00 - 16:00 |
53121 Bonn |
Positive catalogue
Positive catalogue MVA Müllverwertungsanlage Bonn GmbH, please refer to the appendix of the EFB certificate for the approved waste codes
General delivery conditions
Acceptance conditions of MVA Müllverwertungsanlage Bonn GmbH
Annex to the register - Verification no. ENE3MVB00
Limit values
Blank form for analysis parameters
Certificates
Certificate of Returo Entsorgungs GmbH